Slide 3
Slide 3

Inverell Aquatic Centre Redevelopment

Updated September 2024

The new Inverell Aquatic Centre continues to be a hive of activity as construction heads towards completion.

Tilers have commenced tiling the walls of the 50-metre pool and pouring of the concrete for the splash pad will be completed later in the week, weather permitting.

Internal areas are also progressing with the majority of plaster work completed in preparation for fixtures and fittings to be installed, along with tiling works underway in the bathrooms.

The base layer of concrete for the Plant Room pipe work has been completed with construction of the Plant Room to commence shortly.

The Warm Water Program Pool is well under way with reinforcement steel being installed. The pool structure is scheduled to be poured next week.

Completion of the multi-million dollar facility is on schedule for commissioning in late December, with the official opening to be held in early January.

Council has entered into contract with Belgravia Leisure, who will commence operation of Ashford Swimming Pool and the Inverell Aquatic Centre as Facility Managers. The Company has an impressive resume of management experience and Council is looking forward to working with Belgravia Leisure for the benefit of the Community.

Ashford Swimming Pool will open to the public for the season on Tuesday, 1st October 2024.

Warm Water Program Pool.


Western Wall of 50m pool showing tiling works underway.


Tiling of the 50m swimming Pool is well underway the photo depicts the eastern wall of the 50m Swimming Pool.


Works have commenced on the Plantroom with the blinding layer for the pipework being installed.


The photo shows the western wall and northern wall of the 50m Pool.


The photo was taken of the return water pit for the splash pad.


The photo depicts the progress of the warm water pool with reinforcement steel currently being installed.


Photo was taken of the kitchen and Foyer area of the Inverell Aquatic Facility.


Photo show the progress of the two (2) multipurpose rooms.


This photo shows the progress of the footings for the eastern mechanical plant area.


Photo was taken outside the multi-purpose rooms.

Updated June 2024

The video details the progress to date on the construction of the Inverell Aquatic Centre.

Updated February 2024

INVERELL AQUATIC CENTRE REPLACEMENT – UPDATE

On 23 November 2023, the approved Construction Certificate for the Inverell Aquatic Centre was issued. The release of the Construction Certificate is a significant milestone in terms of the project as it now allows physical construction of the Inverell Aquatic facility to commence.

With the release of the construction certificate, Hines Constructions P/L are well underway with the construction of the 50m swimming pool and balance tank. As the majority of works undertaken to date are below existing ground level this provides limited opportunity for members of the public to view the incredible progress of the project.

Hines Constructions P/L are utilising a number of local suppliers and subcontractors in the construction of the new facility.

To enable the community to remain informed, Council will provide regular photos and updates as the construction of Inverell Aquatic Centre progresses.

Any inquiries should be made to Council’s Civil and Environmental Services Division by phoning (02) 6728 8200.

Further background and project development information is available below.

Photo 1: This photo shows the installation of the concrete blinding layer which has been installed over the 150mm drainage layer beneath the 50m swimming pool and the extent of the screw piling which has been installed. The screw piling is connected into the structural reinforcement of the concrete pool structure.


Photo 2: This photo shows the construction progress of the 50m pool balance tank. The photo depicts the installation of structure reinforcement steel for the balance tank walls. Formwork for the balance tank walls is schedule to commence shortly.


Photo 3: Photo 3 was taken from the south eastern corner of the 50m pool balance tank. This photo shows the extent of screw pilling that has been installed under the 50m swimming pool. Approximately half of the concrete blinding layer has been installed with the remain schedule for completion in the coming weeks.


Photo 4: Photo 4 was taken from the western side of the Aquatic Facility building and depicts the extent of screw piling that has been installed under the building.


Photo 5: Photo 5 was taken from the northern end of the 50m swimming pool and shows the installation of the 150mm drainage blanket and collection line and the extent of screw piling that has been installed.

Audio/Visual Fly Through Video

Background Information

Inverell Shire Council has entered into a contract with Hines Constructions P/L for the design and construction of the Inverell Aquatic Centre Replacement.

The $24.98M project got underway in May of this year commencing with the demolition of the existing facility.

Council have been undertaking detailed project development since 2020 which has included extensive community consultation. An initial Feasibility Study was followed by the preparation of a Functional and Technical Design Brief which will inform the detailed design process.

The new facility will include a main 8-lane 50 metre outdoor/indoor pool, a 20 metre by 10 metre warm water pool with moveable floor to maximise the range of uses and an indoor splash park with an associated toddlers pool. State of the art access will ensure ease of use for all ranges of mobility.

The Builder, Hines Constructions are very experienced in the recreational facility construction sector, including the development of numerous aquatic centres in regional NSW.

 

Your Questions Answered

How long will the Swimming Pool be closed for?
It is anticipated the swimming pool will be closed for approximately 18 months with construction work scheduled to be completed in December 2024.

Council acknowledges this will cause disappointment and disruption to some members of the community. The closure is being undertaken in the context of providing a modern aquatic centre that will serve the community for the next 60 years and beyond.

Irrespective of the redevelopment, it would have been necessary to close the pool for a prolonged period this winter and spring to facilitate major repairs and maintenance works. By having a redevelopment plan ready to go and funded it minimises the overall length of time a swimming pool is unavailable to the public.

Why is the Aquatic Centre being replaced?
Detailed condition assessments dating back to 2007 have indicated that major elements of the pool have reached or exceeded their design life.

Council has been faced with increasing challenges to try and keep the facility functioning including significant leaking, failed pipework and fittings, filtration and water reticulation that does not meet modern day standards, failed heating units and elements such as the dividing swim wall that are no longer functional.

The above challenges have seen an exponential increase in operational costs of the facility. Between 2015/16 to 2019/20 there was an approximate 140% increase in the operating cost of the facility.

Feasibility assessment suggested the best long-term option for Council and the community was to replace the existing Aquatic Centre as opposed to repair and refurbishment.

How much will the construction of the new facility cost and how is it to be funded?
Council has entered into a design and construct contract with a maximum ceiling fixed lump sum cost of $24,978,789. Council will be the beneficiary of any savings that come from the detailed design process or the construction.

To date Council has secured grants which total $6,775,000 to part fund the project. The largest contributor to the grant funds includes $5M under the state government Multi-Sport Community Facility Fund. Council will continue to seek grant funding, particularly from the federal government during the detailed design phase of the project.

Consistent with their asset management philosophy and part of the long-term planning for the aquatic centre replacement, has seen Council accumulate over $8,380,000 in dedicated reserve funds that will part fund the project.

Recognising the long-term nature of the project and the principles of intergenerational equity, Council also propose to borrow up to $10M to fund the project.

None of the capital cost, future operating costs or loan repayments will impact on Council’s other core works and services programs and associated capital expenditure.

What will the new facility look like?
The new Inverell Aquatic Centre is designed to provide a ‘one-stop-shop’ for aquatics and health and wellness to serve the needs of the Inverell Shire community as well as the surrounding region and visitors to the area.

The scope of the project will include:

  • An 8 lane 50m x 20m FINA compliant outdoor/indoor pool. The pool will have a roof over the shallow end and a swim wall with a large door to close the opening above. These ‘winterisation’ features will allow for an indoor heated 25 metre pool that meets the specifications for short course racing during the cooler months. The pool will include an access ramp.
  • Integrated 20m x 10m warm water indoor program pool with a spiral lift movable floor (fully moveable to the same depth as well as articulating floor with three integrated depth zones meeting all pool access safety transition requirements). This innovative design element allows a single pool to provide opportunities for both learn to swim and warm water programming which maximises use by younger children through to older adults.
  • Indoor zero depth water play equipment and splash pad with adjacent toddlers pool.
  • New front of house, shared reception/café and moveable retail display areas. Café to be supported by a wet lounge (adjacent to splashpad) and a dry lounge off the foyer.
  • Range of universally assessible change rooms, shower and amenity areas.
  • Multi-purpose activity room for group fitness, community activities and training.
  • Wellness/consulting rooms providing an opportunity or allied health, services or treatment.

What other Aquatic Recreation Options do I have?
The Ashford pool 35 minutes north of Inverell will reman open during the normal swimming season whilst the redevelopment is occurring. Depending on demand Council will look at extending the operating hours of the Ashford Pool.

Other seasonal pools in adjoining shires within 45 minute’s drive from Inverell include Warialda and Glen Innes. Year-round heated pools are available within 1.5 hours drive in both Armidale and Moree.

Private providers with their own pools have supplemented the learn to swim opportunities in Inverell in the past. It is anticipated this will continue and may be expanded due to the closure.

Major funding has recently been expended upgrading the foreshore and facilities at both Lake Inverell and Copeton Northern Foreshores. This provides a range of water experiences for users including the new Splash Park at Copeton Northern Foreshores.

Council will seek to provide access to temporary water play opportunities such as inflatable parks on occasion throughout the normal summer season.

 

Last modified: 25 September 2024

OTHER COUNCIL AFFILIATED WEBSITES

CONTACT COUNCIL

Opening Hours:
Monday - Friday
8:30am - 4:30pm

Correspondence:
General Manager
PO Box 138 Inverell NSW 2360

Administration Centre

144 Otho Street
Inverell NSW 2360

Phone: (02) 6728 8288
Fax: (02) 6728 8277
Email: council@inverell.nsw.gov.au
ABN: 72 695 204 530